Rays say new stadium unlikely to be ready by ’28

Rays say new stadium unlikely to be ready by '28

ST. PETERSBURG, Fla. — A combination of severe hurricane damage to Tropicana Field and political delays on financing means it is highly unlikely the

The commission was meeting again Tuesday on the bond issue, but its chair suggested a vote could be delayed again.

“We know we’re going to be in Steinbrenner in 2025 and we don’t know much beyond that,” Auld said in an interview.

Asked if Major League Baseball can survive long-term in the Tampa Bay area, Rays Principal Owner Stuart Sternberg said the outlook is “less rosy than it was three weeks ago. We’re going to do all that we can, as we’ve tried for 20 years, to keep the Rays here for generations to come.”

The team’s contract with the city of St. Petersburg requires that the Rays play three more seasons at Tropicana Field assuming it is repaired. The cost of fixing the ballpark in time for the 2026 season is pegged at more than $55 million for a building scheduled to be torn down when the new facility is ready.

Under the original plan, Pinellas County would spend about $312.5 million for the new ballpark and the city of St. Petersburg around $417 million including infrastructure improvements. The Rays and their partner, the Hines development company, would cover the remaining costs including any overruns.

It isn’t just baseball that is affected. The new Rays ballpark is part of a larger urban renovation project known as the Historic Gas Plant District, which refers to a predominantly Black neighborhood that was forced out by construction of Tropicana Field and an interstate highway spur.

The broader $6.5 billion project would transform an 86-acre (34-hectare) tract in the city’s downtown, with plans in the coming years for a Black history museum, affordable housing, a hotel, green space, entertainment venues, and office and retail space. There’s the promise of thousands of jobs as well.